MS Project synchronization

1.I worked with MS Project only and I had a number of tasks in it allready. Then I installed and setup Team Foundation Server and Team Explorer. And I began integrate MS Office and TS.

2.I began adding new items to MS Project and publish them into TS

3.One day my MS Project could not connect to TS (with error TF82032)

4.I saw the same problem herehttp://forums.microsoft.com/MSDN/ShowPost.aspx?PostID=312033&SiteID=1

And cleared fields WorkItemID and Rev in MS Project

5.Then MSProject file has connected to TS. BUT

6.When adding new task to MS Project and publishing it to TS, I got a new error TF80038(My old work items have unsupported field values). I think these field values were that I cleared before(see 3 and 4)

7.What can I do?

[967 byte] By [VitaliyVoloshchuk] at [2008-2-19]
# 1

Vitaliy,

Do you still see this problem? If you refresh your plan in Project, does it pull in the work items id information for the old work items?

Try adding new tasks after doing this and publish.

Let me know how it goes.

YogitaManghnani at 2007-9-9 > top of Msdn Tech,Visual Studio Team System,Team Foundation Server - Work Item Tracking...