How do I delte work items?

Is there a way to DELETE work items? Say the pre-defined template for Agile puts in some items which I don't agree wish - and instead wish to start 'a fresh'.

How do I go about deleting work items? So that they would not pollute reports as being closed/completed - even though I did that - just to get rid of them!?

Thank you.

[353 byte] By [RomanT] at [2008-2-21]
# 1

I have responded about deleting work item in http://forums.microsoft.com/MSDN/ShowPost.aspx?PostID=327599&SiteID=1. Please take a look and let me know if you need any more information or help in deleting work items.

-Mohammad

MohammadIqubal-MSFT at 2007-9-9 > top of Msdn Tech,Visual Studio Team System,Team Foundation Server - Work Item Tracking...
# 2

You can customize the process template to not put in those items when a new project is created. Take a look at:

http://forums.microsoft.com/MSDN/ShowPost.aspx?PostID=331518&SiteID=1

Hope this helps.

Rahul Ohri

RahulOhri at 2007-9-9 > top of Msdn Tech,Visual Studio Team System,Team Foundation Server - Work Item Tracking...