Problem in merging & publishing mpps
Hi,
We are using VSTS for the scenario explained below; let me start with background.
Background:
1. We have three different modules in a project.
2. Leads of each module prepare their own mpp.
3. We have some common resources, across the modules.
Assumption:
4. Team lead assumes that, at any point of time, the common resource is available to his module, and prepares the mpp accordingly.
Requirement:
5. a) We need to merge three mpps.
b) We need to perform resource leveling. (Say by project manager).
c) And re-publish the modified mpp to the module leads.
(From 4, it is clear that there is possibility of resource overlapping.)
Steps Performed:
- Created three different areas in VSTS say Area 0, Area 1 and Area 2.
- Created 3 mpps say mpp1, mpp2 and mpp3.
- Set
a)‘Area Path’ of the mpps as ‘Area 0’, ‘Area 1’ and ‘Area 2’.
b)And ‘Work Item Type’ as ‘Task’ for each of the mpps.
- Created one more mpp. (Let us call it as master mpp)
- In the master mpp, click on ‘Get Work Items’, and add all the work items from mpp1, mpp2 & mpp3 to it.
Problems:
1. In the master mpp,
a) Work items are not reflected with the actual duration set in the individual mpps.
b).Start & Finish column are also not reflected.
2. On publishing the merged mpp, the individual mpps (Say mpp1, mpp2 & mpp3) won’t get updated with the merged mpp.
Though the explanation is lengthy I have added it to explain the scenario in details.
Any help in this regard will be highly appreciated.